Meeting on Linac4 - PSB BI Line, 23-November-2009
Present: L. Sermues, M. Scholz, C. Carli, M.
Channel, R. Noulibos, M. Channel, B, Balhan,
M, Hourican, W.Weterings.
Excused: J. Borburgh, R. Chamizo.
- Status H-/0 internal Dump studies (RC) - postponed
- Status BI.SMV magnet calculations (BB)
Bruno presented the current status of the
BI.SMV magnet 3D
analysis. As input was used the 2D magnet design made by Jan and the
latest layout input. The
study is made with a segmented yoke. A prototype of a curved yoke has
been made but proper construction and clamping of a curved coil might be
problematic. The current design allows a beam acceptance of 35mm. For
further details, see
slides.
- Status BI.DIS magnet construction (MH)
Mike presented the
Status of BI.DIS Magnet Construction. One complete magnet system (5
BI.DIS) has been assembled and inserted in the vacuum tank. A special
tooling was developed to guide the magnets in the tank by removable rails. A
30kV feedthrough was developed and successfully tested and the resulting
design will be used for the BI.DIS, although the current PFN design only
requires ~5kV due to the fact that the 25Ω impedance
could be reduced to 5Ω. Finalizing the feedthrough design with multicontact
connexions still remains to be done.
- BS magnets with ceramic vacuum chambers (WW)
Wim presented possible vacuum variants
for the BS magnets. The magnets could be assembled inside vacuum tanks.
This is feasible, but large bulky tanks are required to house the magnets.
Furthermore, bake-out will be required and intervention will be difficult and
time-consuming, specially for intervention on one of the lower ring magnets,
when both tanks will need to be removed. The use of undulated Inconel chambers
has also been studied, but the influence of the eddy current effects and
resulting optics perturbations have not yet been fully understood. (see
also related meeting). The possibility of using ceramic chambers was
also studied, this option would be feasible, but aperture restrictions for
BS1 due to the increased thickness of the chamber still need to be resolved.
Furthermore, the procurement and price of ceramic chambers could be an
issue.
- AOB
WW