Meeting on Linac4 - PSB BI Line,
16-February-2009
Present: Jan Borburgh; Christian Carli;
Rocio Chamizo; Michael
Hourican; Luc Sermeus; Wim Weterings;
- The major milestones for 2009 were discussed and the following where
identified:
- Complete the conceptual design of the Injection process and Painting
schemes by July 2009.
- Build a BS magnet prototype in order to
measure multipoles and influence of vacuum chamber.
- Complete conceptual design of stripping unit and built prototype
foil changer.
- In order to study the influence of the proposed
inconel vacuum chamber of the
BS magnets, JB suggested to perform magnet tests with PS42 bumper magnets.
Two identical magnets exist, one with and one without vacuum chamber.
- The proposal for extracting
the Head Dump was discussed and RC expressed her doubts on the
feasibility of an external dump. It was decided that for the next meeting
the proposal would be completed with cost and activation estimates.
WW