WW reported on the Linac4
workpackage holders meeting of 22 April, showing slides of the
status of project
and some general communications, information about
project documents and templates, EDMS and the
EVM implementation. It was noted that a new work package (2.13 Beam
intercepting devices, Y. Kadi AB/ATB) has been added to the
LINAC4
work breakdown structure. BG proposed to invite Y.Kadi to one of our
future meetings in order to discuss issues concerning the head-tail dump as
well as the unstripped H-dump.
JB reported on the ongoing feasibility study concerning BI.BS
magnet fall time. The field delay due to
eddy currents in a vacuum chamber for a out of vacuum BS magnet were
estimated by MC. As a base
results of the out of vacuum BS magnet presented in the previous meeting
were used. A magnet gap of 80 mm was assumed. The dB/dt was chosen 740 mT/ms,
corresponding to a 1ms fall time of BI.BS3, giving a delay of 67 μs.
A prototype magnet is being built to verify the calculated eddy current
data.
BB reported that the price enquiry for the BI.DIS
ferrites is in ongoing.