Meeting on Linac4 - PSB BI Line, 26-January-2007

Brennan Goddard; Tony Fowler; Jan Borburgh; Luc Sermeus; Wim Weterings.

- Status ongoing work
- Foil heating simulations
- AB- Report
- Internal dump
- PSB BI Functional Specification
- Detailed layout of Beam Injection region

- The status of the action list was discussed:

ACTIONS LIST:

Name Action Results
BG, GB Optics Matching at Injection point Still ongoing
KH Beam offset at BI.DIS 5.2mm baseline solution, as in TDR
WW, JB, TF, LS cost / time estimate backwards compatible system estimates
BG Fall time specification KSW Presentation
? Fringe field specification  
FG duration or elimination of the head and tail Timing estimates
BG Possibility of vertical painting  
ALL AB-BT note on LINAC4 Proposed layout (deadline - may 2007)
GB Collimation of injected beam before BI.DIS  
WW Foil Heating Simulations CNGS_2μm foil, CNGS_5μm foil, _

WW